The Technology and Construction Court ( “TCC” ) in the recent case of   Grove Developments   Limited   – v – Balfour Beatty Regional Construction Limited [2016] EWHC 168 (TCC) looked at   whether   or not a contractor was entitled to interim payments for works carried   out after   an agreed payment schedule between the parties had expired.

The parties entered into a JCT D&B Contract 2011 (DB11), with amendments from the Employer. The works were for the design and construction of hotel and serviced accommodation beside the O2 Complex in London. The contract value was in the region of   £121m    Works began in July 2013 and were to be completed by July 2015.

The parties had agreed there would be stage payments in accordance with Alternative A of the JCT DB11 These stage payments stated that there would be 23 no. payments throughout the duration of the contract, between July 2013 and July 2015 when the works were to be completed    On 21 August 2015, one month after the works were to have been complete d, the   Contractor issued an   interim application , for Payment No    24. This   application was valued by   the Contractor in the region of £23 million and made pursuant to the payment regime under the   Housing Grants , Construction Regeneration Act 1996 (“ the Act ”)    Grove Developments   (“ Grove ”)   responded to Balfour Beatty stating that they had no   contractual right to issue Interim   Application 24 , and that the payment regime   under the Act   was irrelevant as the Contract has   established a mechanism and dates for payments    In any event, Grove also argued that a valid   payless notice had been issued.

Balfour Beatty commenced adjudication   proceedings and in January 2016 t he Adjudicator   issued his decision stating that Grove should pay Balfour Beatty a   further £2 million , in addition to the sums already paid, thus approving payment Application No    24.

However, in December 2015, whilst the adjudication was still on – going , Grove   started Part 8   Proceedings in t he High Court. Part 8 proceedings are for declaratory relief , and in this   instance Grove sought the Court’s determination that   Balfour Beatty had no right to be paid for   Application No    24   as the parties   had already   agreed under contract that there would   be   only   23   staged payments throughout the duration of the Contract

In making his decision Stuart – Smith J referred to the   Act, which provides the statutory payment   regime that applies to construction contracts. This is read in conjunction with Part 2 of the   Scheme for Construction Contracts (England and Wales) Regulations 1998.

Sections 109   – 110   of the Act   state that   1)   there is an entitlement to stage payments and   2)   that there   must be an adequate mechanism for determining when the se stage payments   would apply. Stu art – Smith J considered recent case law , including his own judgement in   Yuanda , stating that if there are existing contractual arrangements that are capable of coexisting with the Scheme, being that there are   adequate provisions for interim stage payments, then it is unnecessary to import the Scheme’ s payment provision   as a whole. This is what Balfour Beatty was attempting to do for payment   application No. 24

Ultimately, Stu art – Smith J concluded that as the parties had   agreed to the interim staged payments, as   well as the amounts of each interim payment, the fact that the agreement did not provide for interim   payments covering work taking place   after the stage payments , was not enough to import the   Scheme’s payment provisions to supplement the agreement already   in place      Essentially this would   have created a contract with two payment regimes, a contractual and a statutory one   existing parallel   with each other.

The lessons to learn from this decision   are two – fold. First contractors must ensure they understand the   payment terms and schedule for payments they sign up to    Second, if   there is   a specific schedule of   interim payments agreed at the outset of the contract, contractors will need to ensure that w h ere work   is carried out after the stage payment s expire , there   exist provisions to apply for additional payments      From   a strict interpretation of the Court’s decision, which some may consider harsh , the contract or shall have no contractual right to apply for further payments for work carried out after agreed interim stage payments have expired until the final payment mechanism kicks in after practical completion.   Even though the Grove failed to include such a provision, this was not enough to allow the Contractor   to import   the Scheme’s payment provisions to supplement what had been fairly and adequately   agreed.

This decision ultimately highlight s the importance and need for contractors to be diligent and clear in their understanding when agreeing to scheduled stage payments, as well as the requirement for them   to have an agreed mechanism for additional payments whenever work is carried out beyond the   agreed Schedule.

Main contractors must be aware when agreeing to staged payment schedules, as if these payment   terms are not   imposed downstream to subcontractors and supply chains, main contractors will stand to   be exposed and at extreme risk of   cash flow irregularity

The Technology and Construction Court ( “TCC” ) in the recent case of   Grove Developments   Limited   – v – Balfour Beatty Regional Construction Limited [2016] EWHC 168 (TCC) looked at   whether   or not a contractor was entitled to interim payments for works carried   out after   an agreed payment schedule between the parties had expired.

The parties entered into a JCT D&B Contract 2011 (DB11), with amendments from the Employer. The works were for the design and construction of hotel and serviced accommodation beside the O2 Complex in London. The contract value was in the region of   £121m    Works began in July 2013 and were to be completed by July 2015.

The parties had agreed there would be stage payments in accordance with Alternative A of the JCT DB11 These stage payments stated that there would be 23 no. payments throughout the duration of the contract, between July 2013 and July 2015 when the works were to be completed    On 21 August 2015, one month after the works were to have been complete d, the   Contractor issued an   interim application , for Payment No    24. This   application was valued by   the Contractor in the region of £23 million and made pursuant to the payment regime under the   Housing Grants , Construction Regeneration Act 1996 (“ the Act ”)    Grove Developments   (“ Grove ”)   responded to Balfour Beatty stating that they had no   contractual right to issue Interim   Application 24 , and that the payment regime   under the Act   was irrelevant as the Contract has   established a mechanism and dates for payments    In any event, Grove also argued that a valid   payless notice had been issued.

Balfour Beatty commenced adjudication   proceedings and in January 2016 t he Adjudicator   issued his decision stating that Grove should pay Balfour Beatty a   further £2 million , in addition to the sums already paid, thus approving payment Application No    24.

However, in December 2015, whilst the adjudication was still on – going , Grove   started Part 8   Proceedings in t he High Court. Part 8 proceedings are for declaratory relief , and in this   instance Grove sought the Court’s determination that   Balfour Beatty had no right to be paid for   Application No    24   as the parties   had already   agreed under contract that there would   be   only   23   staged payments throughout the duration of the Contract

In making his decision Stuart – Smith J referred to the   Act, which provides the statutory payment   regime that applies to construction contracts. This is read in conjunction with Part 2 of the   Scheme for Construction Contracts (England and Wales) Regulations 1998.

Sections 109   – 110   of the Act   state that   1)   there is an entitlement to stage payments and   2)   that there   must be an adequate mechanism for determining when the se stage payments   would apply. Stu art – Smith J considered recent case law , including his own judgement in   Yuanda , stating that if there are existing contractual arrangements that are capable of coexisting with the Scheme, being that there are   adequate provisions for interim stage payments, then it is unnecessary to import the Scheme’ s payment provision   as a whole. This is what Balfour Beatty was attempting to do for payment   application No. 24

Ultimately, Stuart – Smith J concluded that as the parties had   agreed to the interim staged payments, as   well as the amounts of each interim payment, the fact that the agreement did not provide for interim   payments covering work taking place   after the stage payments , was not enough to import the   Scheme’s payment provisions to supplement the agreement already   in place      Essentially this would   have created a contract with two payment regimes, a contractual and a statutory one   existing parallel   with each other.

The lessons to learn from this decision   are two – fold. First contractors must ensure they understand the   payment terms and schedule for payments they sign up to    Second, if   there is   a specific schedule of   interim payments agreed at the outset of the contract, contractors will need to ensure that w h ere work   is carried out after the stage payment s expire , there   exist provisions to apply for additional payments      From   a strict interpretation of the Court’s decision, which some may consider harsh , the contract or shall have no contractual right to apply for further payments for work carried out after agreed interim stage payments have expired until the final payment mechanism kicks in after practical completion.   Even though the Grove failed to include such a provision, this was not enough to allow the Contractor   to import   the Scheme’s payment provisions to supplement what had been fairly and adequately   agreed.

This decision ultimately highlight s the importance and need for contractors to be diligent and clear in their understanding when agreeing to scheduled stage payments, as well as the requirement for them   to have an agreed mechanism for additional payments whenever work is carried out beyond the   agreed Schedule.

Main contractors must be aware when agreeing to staged payment schedules, as if these payment   terms are not   imposed downstream to subcontractors and supply chains, main contractors will stand to   be exposed and at extreme risk of   cash flow irregularity.

This article was originally written and published on the internet by Quigg Golden in 2017.

 

This document (and any information accessed through links in this document) is provided for information purposes only and does not constitute legal advice. Professional legal advice should be obtained before taking or refraining from any action as a result of the contents of this document.

 

BDAS specialise in: providing contract advice, resolving construction disputes, managing construction claims & adjudications and will give you competitive, independent advice tailored to your specific construction problems.

If you could benefit from this please call Jon now on 07795 231 231 or email: Jon@BDASweb.com

 

.