The right to terminate a construction contract for reasons such as poor performance is a crucial contractual right. However, if exercising the right to terminate is not carried out in accordance with the contractual notice requirements then a party risks invalidly terminating the contract, and exposing itself to a wrongful termination action. Recent case law in the UK and Australia serves as a timely reminder that a valid or invalid termination can start with the contractual “default” notice.

Default Notices and Termination

Many contracts require a “default” notice before a termination notice is issued. A default notice alerts a party to the reasons why the other party believes that the party is in breach of contract. The default notice requires the party receiving it, within a stated amount of time, to take steps to remedy the identified issues on a project and / or to explain why the party is not, or is no longer, in breach of contract. The primary aim of a contractual notice regime is to provide a party in breach the opportunity to remedy the notified breach and to avoid termination. If the issues persist then default notices become part of the necessary contractual requirements for a valid termination.

Recent Cases – Failure to Issue and Inadequate Default Notices 

In the recent English High Court (Technology and Construction Court) decision, Interserve Construction Limited v Hitachi Zosen Inova AG [2017] EWHC 2633 (TCC), the Court considered the application for declaratory relief by Interserve Construction Limited (ICL), a design and build subcontractor, to Hitachi Zosen Inova AG (HZI), an EPC contractor, for the construction of an energy-from-waste plant in Hartlebury, Worcestershire. HZI sought to terminate ICL due to HZI’s alleged poor performance including alleged delay: ICL relied on clauses in the contract that provided grounds for termination based on a failure “to proceed regularly and diligently with the Works” and ICL was removed from site. HZI did not issue a default notice prior to terminating ICL.

What does a Default Notice Need to Say?

Recent Australian cases have also considered the requirements for a valid default notice (often referred to as a “show cause” notice under many Australian standard form construction contracts). In the ACT Court of Appeal decision, R Developments Pty Ltd v Forth [2017] ACTCA 38, the Court considered whether a builder that had terminated a contract with the owners of a residential construction had done so validly. The builder claimed to have terminated the contract because the owners had failed to supply evidence of their capacity to pay the contract price. The contract contained two terms concerning the owners’ obligations that were relevant to the case: (i) an obligation to give evidence to the builder that the owners had obtained finance from a lending authority; and (ii) an obligation that the owners give evidence to the builder of their ability to pay the contract price. Crucially, in its default notice, the builder relied only upon the owners’ failure to supply evidence of their capacity to pay the contract sum and did not refer to the contractual clause requiring evidence of the owners’ giving evidence of having obtained finance.

If a contract requires it, a party must also give precise details in the default notice as to the time for a response, in order for the other party to have an adequate opportunity to rectify it. In Westbourne Grammar School v Gemcan Constructions Pty Ltd [2017] VSC 645, the contract required the default notice to include the date and time by which the builder would have to “show cause” (i.e. either provide an explanation of why it was not in breach of contract or take steps to remedy the alleged default). In this dispute, the default notice issued by Westbourne Grammar School merely stated that “[y ou must show cause by the expiration of 7 clear days after this notice is received by you.” The Supreme Court of Victoria found this notice to be inadequate because it failed to specify the date and time for compliance, but rather placed a timeframe around the unspecified time of receipt of the notice by the builder. The Court observed that: “[t]he notice is of critical importance to both parties” and that a proper notice “was designed to put beyond any doubt the time and date by which the builder had to show cause.”

Conclusion

Conclusion The above cases confirm the importance that a default notice must be issued before termination rights are exercised, if the contract so requires. Furthermore, clauses supporting termination must be referred to in the notice as well as adequate details of the breach, and, if the contract requires it, adequate identification of the time to respond to the notice. This content can be the difference between a valid and an invalid termination. The importance of avoiding a wrongful termination must never be underestimated: a successful action for wrongful termination can result in an award of damages that may include payment of the remainder of money due to the contractor for work performed up to the date of termination and other payments due under the contract. Damages may potentially also include extensive other payments such as payments for loss of profits.

 

This article was originally written and published on the internet by White & Case on 07/02/18.

 

This document (and any information accessed through links in this document) is provided for information purposes only and does not constitute legal advice. Professional legal advice should be obtained before taking or refraining from any action as a result of the contents of this document.

 

BDAS specialise in: providing contract advice, resolving construction disputes, managing construction claims & adjudications and will give you competitive, independent advice tailored to your specific construction problems.

If you could benefit from this please call Jon now on 07795 231 231 or email: Jon@BDASweb.com